Section 1.2, Scope

Scope

This document will be used:

  • by applicants to prepare a licence application for a licence to construct a proposed new reactor facility at a new or existing site
  • by CNSC staff to assess the licence application 

Where appropriate, this document may be used in conjunction with REGDOC‑1.1.5, Supplemental Information for Small Modular Reactor Proponents [1].

Note: This application guide covers facility design, construction and fuel-out commissioning. It also provides information that should be considered in planning for operation.